Jefferson Central School

"To Serve our Children is our Purpose"


 
Building Project Update

Capital Project Update:  Design Phase
October 2008

This capital project will renovate and reconstruct key areas of our buildings in order to improve the safety, efficiency, appearance, and usefulness of our school facilities.  We will renovate the kitchen, cafeteria, music classroom, and administrative offices; restore the district's stage, which was decommissioned in 1989; upgrade the district's heating and ventilation systems; replace windows and doors; upgrade our fire alarm, public address, and master clock system; restore exterior masonry; enhance building security and accessibility; and improve our three parking lots.  The project will also add 7,200 square feet of instructional space to our building.  This addition will house a new library/media and computing center, new technology classroom, and an expanded gymnasium.

Our planning for the upcoming Capital Project continues to move forward.  Here's a look at our progress this past month...

*        Our architectural team met with the Board of Education last month to review the floor plans and exterior renderings.

*        Our Superintendent and Business Office Manager met with our architects, fiscal advisor, and bond counsel to discuss our short-term cash needs and establish a borrowing schedule.

*        The Board of Education has approved the issuance of a $950,000 bond anticipation note to fund project expenses through June 2009.

*        Our architects will submit our entire set of construction plans to the State Education Department for review by the end of October.

*        We anticipate a 16-week waiting period before officials actually review our plans; during that time, our architectural team will continue to fine- tune the plans.

*        Our architects will be presenting a preliminary "phasing" schedule to the Superintendent on October 29.  Following his review of the phasing schedule, the district's Site Team will be convened to provide feedback on the schedule.

*        A new construction manager has been assigned to our team by CSArch Mr. Scott Wolfe, who has extensive experience overseeing K-12 school construction projects, will replace Mr. Andrew Jablonsky.

*        Our Site Team will meet with the architects in early December to review a first draft of the project phasing schedule.

Following SED approval of our plans, we will begin to prepare our bid documents in anticipation of putting the project "out to bid" in Spring 2009 and beginning construction in Summer 2009.

 
 
Project Phasing

 


Pre-Referendum

Facilities

Programs Review

Conceptual

Cost-Estimating

Public Outreach

 

Post-Referendum

Design & SED Approval

Bid Preparation

Bid Solicitation

Awarding of Bids

Renovation and Construction

Final Inspection

 

 

 

Architect

 

Greg Klokiw, Project Manager

CS Arch, PC

Albany, NY
 

Construction Manager

 

Scott Wolfe

CS Arch, PC

Albany, NY

 

Financial Advisor

 

Benjamin Moslona

Fiscal Advisors and Marketing

Syracuse, NY

Jefferson Central School